Pipe sizing questions look like the hardest thing on the G3 exam and are the most mechanical once you know the order. It is the same four steps every time.
Where a value falls between two, take the larger one. Every time.
Natural gas uses Annex A; propane uses Annex B. Inside each, pick the sub-table matching the material — steel pipe or copper tubing. Reading the right table is half the marks; the arithmetic is the easy part.
Every pipe sizing question on the exam is one of ten shapes. Recognising which one you are looking at tells you what to do before you touch a table.
| # | Scenario | How you know |
|---|---|---|
| 01 | Straight run | Only one appliance shown, no tees |
| 02 | Single pipe system | Several appliances, one material, tees shown |
| 03 | Combination system | Two materials, such as steel and copper |
| 04 | Manifold system | The word "manifold" appears in the question |
| 05 | Find the missing pipe size | One section marked with a "?" |
| 06 | Find the maximum BTU | Pipe size given, asks for capacity |
| 07 | Column selection only | "Which column?" or "Is this correct?" |
| 08 | Medium pressure | Supply pressure given in psig, above 14" w.c. |
| 09 | System extension | The words "adding" or "extending" an appliance |
| 10 | Propane system | "Propane" or "LP" mentioned — Annex B, not A |
LMR stands for Longest Measured Run — the distance from the meter to the farthest appliance on the system. It is always the longest single path, and it is the first thing to establish when sizing pipe.
Find the Longest Measured Run, choose a column value at or above that length rounding up, add the total BTU/h load carried by the section, then read down that column to the first pipe size whose capacity meets or exceeds the load — again rounding up.
Always up. Round the column value up to at least the measured run, and take the first pipe size whose capacity meets or exceeds the load. Where a value falls between two, take the larger.
Natural gas systems use the Annex A tables and propane uses Annex B. Within each, use the sub-table matching the material — steel pipe or copper tubing.